EXAMPLE: Resource availability overrides critical status
If one tape drive is available, neither job is submitted. When two tape drives become available, job EBDUPDT is submitted.
Job EBDUPDT’s priority level is 50, Critical is selected, and it requires two tape drives.
Item |
Value |
---|---|
File Name |
EBDUPDT |
Quantitative Resources |
TAPE 0002 |
Priority |
50 |
Critical |
Y |
Job EBDEXEC’s priority level is 04, and it requires one tape drive. It is not a Critical job.
Item |
Value |
---|---|
File Name |
EBDEXEC |
Quantitative Resources |
TAPE 0001 |
Priority |
04 |
Critical |
N |
EXAMPLE: Resource availability determines job submission
If one or two tape drives are available, neither job is submitted. When three tape drives become available, job EBDBKP is submitted.
Job EBDBKP’s priority level is 8A, Critical is selected, and it requires three tape drives.
Item |
Value |
---|---|
File Name |
EBDBKP |
Quantitative Resources |
TAPE 0003 |
Priority |
8A |
Critical |
Y |
Job EBDMAINT’s priority level is 70, Critical is selected, and it requires one tape drive.
Item |
Contents |
---|---|
File Name |
EBDMAINT |
Quantitative Resources |
TAPE 0001 |
Priority |
70 |
Critical |
Y |